Investigation Report

Tubing Hanger Pin Ejection During Temporary Well Abandonment

BSEEBureau of Safety and Environmental Enforcement

10-27-2011 01:00 G04090 WC/294 Required Evacuation - LTA (>3 days) - Other

Read at BSEEOpens the document on bsee.gov

Summary

Investigation of a tubing hanger pin ejection during temporary well abandonment, causing a fractured shin. A defective fitting allowed hydraulic fluid into a wellhead void, compressing trapped air or gas. Findings address unrelieved pressure, improper pin removal, unavailable tools, supervisory training oversight and incomplete job safety analysis.

Topics

About This Record
Original title
10-27-2011 01:00 G04090 WC/294 Required Evacuation - LTA (>3 days) - Other
Publisher
Bureau of Safety and Environmental Enforcement
Type
Investigation Report
Date
Unknown
Topic
Line of Fire, Mechanical Failure, Pressure Systems
Activity
Well Abandonment
Equipment
Wellhead
Control
Competence and Training, Energy and Process Isolation, Job Safety Analysis, Operational Supervision
Sector
Upstream Oil and Gas
Link
Checked , working