Equinor - Johan Castberg - investigation of the reasons for the challenges faced in constructing hull and equipment
Read at HavtilOpens the document on havtil.no
Summary
Investigation into weld-quality problems and fatigue-analysis errors during construction of the Johan Castberg hull and integrated living quarters. It examines contractor oversight, inspection competence, non-destructive testing and verification independence. Findings identify inadequate welding expertise and quality assurance, persistent unresolved risks, strained multi-yard follow-up and delayed communication to licensees.