Investigation Report

Wellhead Gas Leaks During Production Restoration After Hurricane

BSEEBureau of Safety and Environmental Enforcement

10-31-2008 14:30 G01146 VR/245 Surface Equipment Failure or Procedures

Read at BSEEOpens the document on bsee.gov

Summary

Investigation of wellhead gas leaks during restoration of platform production after Hurricane Ike. Stretched flange studs compromised seals, while Well G-4’s SCSSV initially failed to seal. The report describes flaring, component replacement and testing, and recommends post-event inspections, isolation and wellhead pressure tests before reopening SCSSVs.

Topics

About This Record
Original title
10-31-2008 14:30 G01146 VR/245 Surface Equipment Failure or Procedures
Publisher
Bureau of Safety and Environmental Enforcement
Type
Investigation Report
Date
Unknown
Topic
Hydrocarbon Release, Mechanical Failure, Well Control, Well Integrity
Activity
Inspection and Maintenance, Pressure Testing
Equipment
Valve, Wellhead
Control
Energy and Process Isolation, Well-Barrier Testing
Sector
Upstream Oil and Gas
Setting
Offshore Installation
Link
Checked , working
Record
bsee-a67d8a4d93 · added 2 October 2026